Pilbara Iron Ore and Infrastructure Project: Port and North-South Railway (Stage A)

Project
Proposal description

The proposal has the following main components:

  • a 345 km railway line from Port Hedland to proposed mining operations at Mindy Mindy. This railway will be constructed in two parts: Part 1 from Port Hedland to the Chichester Ranges and Part 2 from the Chichester Ranges to Mindy Mindy;
  • construction of port facilities consisting of rail loop, car dumper, stockyard and ore handling facilities (including two stackers and a single reclaimer), rescreening facility and product conveyor out to a wharf and shiploader at Anderson Point in Port Hedland.
Assessment Number
1505
Region
Referred under EP Act
s38
Industry sector
Last updated
Current Status
Ministerial Statement published
2. Decision on whether to assess this proposal
3. Assessment
Scoping
Approved
Environmental Review
4. EPA Report on assessment
EPA Report Number
1173
Date published
Appeals close
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval
Post-assessment changes
s. 45C amendments

Attachment 1 to Statement 690 - Increase of dredging area and clearance area for Port - 45C change to proposal approved on 6 April 2006.

Attachment 2 to Statement 690 - Additional clearance for temporary access road - 45C change to proposal approved on 17 August 2006.

Attachment 3 to Statement 690 - Additional infrastructure listed as part of Rail Loop and Railway Alignment - 45C change to proposal approved on 12 September 2006.

Attachment 4 to Statement 690 - Increase of dredging area and clearance area for Port - 45C change to proposal approved on 27 April 2007.

Attachment 5 to Statement 690 - Description of conveyors as uncovered - 45C change to proposal approved on 4 April 2008.

Attachment 6 to Statement 690 - Extension of construction period and addition of two car dumpers - 45C change to proposal approved on 7 August 2008.

Attachment 7 to Statement 690 - Additional rail infrastructure and associated clearance of an additional 606 hectares - 45C change to proposal approved on 17 December 2009.

Attachment 8 to Statement 690 - Increase in railway corridor disturbance (371 hectares) due to construction of additional infrastructure, increase in port operating area (3 hectares) due to widening of causeway – section 45C change to proposal approved on 21 August 2011.

Attachment 9 to Statement 690 – Remove and amend the port elements of Schedule 1 to include wharf AP5, and removal of references to export tonnage in Schedule 1 – change to proposal approved under section 45C on 6 February 2014.

Date of approval s. 45C
Get notified of updates and new content

Login to Subscribe to this page | Subscription Info

Printer Friendly, PDF & Email