Duplication of iron ore mining operation, Yandi mine ML 270SA, Hamersley Range
Project
Proposal description
The proposal is to develop a second open-cut iron ore mining operation on Mineral Lease 270SA. Known as the Central Mesa 1 and 2 operation, the new proposed mine site is located in the Hamersley Ranges of the Pilbara Region of Western Australia. The proponent proposes that a lease-wide Environmental Management Programme be developed and apply to both the Central Mesa 1 and 2 mine, the Yandi E2 mine and future operations on Mineral Lease 270SA.
The proposed second iron ore mining operation, Yandi C1/C2, is located on resources totalling approximately 200 Mt. Lowering of the present water table by approximately 40 m is necessary to recover all of the economic ore. The operation will be serviced by an additional rail spur of approximately 10 km length, terminating in a loop. The crushing, screening and trainloading facilities will essentially be a duplication of the infrastructure already in place to serve the existing Yandi E2 operations.
Referred under EP Act
s38
Last updated
February 06, 1998
Current Status
Ministerial Statement published
2. Decision on whether to assess this proposal
Date published
Saturday, 24 June, 1995
3. Assessment
Scoping
Approved
Friday, 28 July, 1995
4. EPA Report on assessment
Date published
Friday, 8 December, 1995
Appeals close
Friday, 22 December, 1995
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval
Monday, 5 February, 1996
Post-assessment changes
s. 45C amendments
Attachment to Statement 405 - extension of time limit for submission of decommissioning plan to 31 December 1998 - change to proposal approved on 6 February 1998.