Staged expansion of Tiwest Pigment Plant to 180,000 tpa, Kwinana

Project
Proposal description

The proposal is to increase the production capacity of Tiwest's titanium dioxide plant at Kwinana. The proposal is to modify/expand the existing plant to allow an increase in production capacity from 80,000 tonne per annum (tpa) to 180,00 tpa of titanium dioxide pigment in three notional stages:

  1. Stage I: increase to 120,000 tpa,
  2. Stage 2: increase to 165,000 tpa and
  3. Stage 3: increase to nominally 180,000 tpa.

The first and second stages of the expansion wilI require major modifications to the plant (plant infrastructure to achieve 180,000 tpa capacity will be developed during Stage 1 construction and approximately 85% of the mechanical process equipment will be installed in Stage 1). Stage 3 expansion will depend upon technological and commercial viabilities and will require minor modifications.

Assessment Number
1039
Region
Referred under EP Act
s38
Industry sector
Last updated
Current Status
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination
Date published
3. Assessment
Scoping
Approved
Environmental Review
4. EPA Report on assessment
EPA Report Number
847
Key Environmental Factors
Date published
Appeals close
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval