The proposal is to supply power to an expanded mining operation at the Telfer Gold Mine.

The proposed expansion of the Telfer Gold Mine associated with this proposal is being dealt with separately. That mine expansion is set out in a separate referral to the EPA (Newcrest Mining Limited 2002b).

The mine expansion and power supply proposals have been separated because it is likely that the mine and power supply will eventually be operated by different proponents. Nevertheless, the proposals have been developed and assessed in parallel.

The EPA's assessment of the mine expansion proposal is here.

Assessment Number
1444
Region
Referred under EP Act
s38
Industry sector
Last updated
Current Status
Ministerial Statement published
2. Decision on whether to assess this proposal
Preliminary Environmental Factors
Date published
3. Assessment
4. EPA Report on assessment
EPA Report Number
1058
Key Environmental Factors
Date published
Appeals close
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval
Post-assessment changes
s. 45C amendments

Attachment 1 to Ministerial Statement 605 - alteration to pipeline route from Port Hedland to Telfer - change to proposal approved under s45C on 19 August 2004.

Attachment 2 to Ministerial Statement 605 - Consolidation and Amendment of Key Characteristics Table, Option 1a. Supplying natural gas from Port Hedland via a buried pipeline to the Telfer Gold Mine for on-site electricity generation at a new open cycle gas fired power plant - change to proposal approved under s45C on 2 May 2012.

Date of approval s. 45C