This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: December 12, 1997
The proposal is to establish the Geraldton Steel Plant (GSP) at Oakajee, 23km north of Geraldton. The GSP will be located within the planned Oakajee Industrial Estate in the Shire of Chapman Valley. The proposal will consist of the following main components: a pellet plant in which the majority of iron ore is converted to pellets suitable for direct reduction; two direct reduction plants for the reduction of pelletised iron ore to direct reduced iron; three electric arc furnaces and tlu·ee... Read more...Last updated: November 6, 1997
The proposal includes the following key features: construction and operation of a metallurgical limestone mine; production of quicklime at a quicklime plant to be located at the mine; road transportation of limestone and quicklime through Exmouth; and shipping of limestone and quicklime from the Point Murat jetty. Read more...Last updated: October 13, 1997
The proposal is to to increase the production of Kingstream Resources' recently assessed Mid West Iron & Steel Project Geraldton Steel Plant (GSP), at the Narngulu Industrial Estate south-east of Geraldton, from 1.0 Mt/a to 2.4 Mt/a. Changes are also proposed to the product, specifically that slab steel be produced rather than rolled coil, with resulting changes in the requirement for major plant. Read more...Last updated: July 14, 1997
The proposal is to construct a pipeline fabrication site within the exrstmg Mardie Station Pastoral lease and existing Vacant Crown Land Reserve, approximately 45km south west of Dampier and 15km east of Cape Preston is detailed in the CER. Read more...Last updated: June 30, 1997
The proposal is to increase the production capacity of Tiwest's titanium dioxide plant at Kwinana. The proposal is to modify/expand the existing plant to allow an increase in production capacity from 80,000 tonne per annum (tpa) to 180,00 tpa of titanium dioxide pigment in three notional stages: Stage I: increase to 120,000 tpa, Stage 2: increase to 165,000 tpa and Stage 3: increase to nominally 180,000 tpa. The first and second stages of the expansion wilI require major modifications to... Read more...Last updated: May 19, 1997
The proposal is to to expand NufarmCoogee Pty Ltd's Chlor-alkali Plant at Kwinana to allow an increase in chlorine gas production to 42,000 tonnes per annum (tpa) through the installation of a new electrolysis processing circuit. Storage of chlorine held on site will rise from a nominal 50 tonnes to 150 tonnes. Read more...