Pardoo Direct Shipping Ore Project Port Hedland

Project
Proponent
Proposal description

The proposal is to develop and operate a direct shipping iron ore project in the Pilbara. The project involves the open-cut mining of eight small pits approximately 70 kilometres east of Port Hedland to obtain direct shipping ore quality haematite. Annual ore production will be 1.5 million tonnes.

Assessment Number
1685
Region
Referred under EP Act
s38
Industry sector
Last updated
Current Status
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination
Extract of determination
Date published
3. Assessment
4. EPA Report on assessment
EPA Report Number
1289
Date published
Appeals close
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval
Post-assessment changes
s. 45C amendments

Attachment 1 to Statement 775 - Multiple project design and operational changes to the mine site - section 45C change to proposal approved on 25 August 2009.

Attachment 2 to Statement 775 - Increase the mining rate from 1.5 to 3 million tonnes per annum, involving the addition of two new open pits and associated infrastructure, and changes to an existing open pit – change to proposal approved under s45C on 6 July 2010.

Attachment 3 to Statement 775 – Increase the volume of annual dewatering and environmental discharge from 2 GL per annum to 4.0 GL per annum – change to proposal approved under section 45C on 24 May 2012.

Attachment 4 to Statement 775 - Increase the volume of annual dewatering and environmental discharge from 4 GL to 10 GL per annum, and increase in total disturbance footprint from 490.4 ha to 501.7 ha – change to proposal approved under section 45C on 24 July 2012.

Date of approval s. 45C